Thank you to my parents for visiting!
Sunday, January 2, 2011
Staircase
The internal MDF stairs were erected while we were away on our Christmas break, to our surprise.
Saturday, December 25, 2010
Painting
The painters arrived on Christmas Eve to start painting the exterior...
Painting Lightcourt 1
Painting started to the weatherboards outside...Gee I hope they remove the ivy to that gutter.
The verandah also looks rather precarious...waiting for the builder to fix that up.
Do I like the smell of fresh paint or what....
Looks new and refreshed....
The upper terraces are also tanked.
Friday, December 24, 2010
Thursday, December 23, 2010
Glazed
The glass has finally been installed - Lightcourt 2
The large skylight over the kitchen has been glazed too!
Skylight over our study area
What a mess....at least the contractors are on site and working!
Lots of conduits
The roof plumber doing acrobatics up on the roof....
Saturday, December 18, 2010
Front garden demo
Demolition of the front garden...
What's left of the fence overgrown with ivy
The glass has arrived
More plumbing rough-in
Rubbish out the backyard....
Sunday, December 12, 2010
Roughing-in
The framing around the fireplace started
The foilboards are also all installed to the concrete walls
Jason busy cleaning out the woodchips and sawdust in the window frames before the glazing goes in...
Look at all the sawdust stuck inside the frames....heartbreak....
The electrician has cut the foilboards to prepare to rough in the electrical conduits
The kitchen bulkhead
The soffit is done too
Electrical rough-in
Depressing...the insulation is a heap on the floor. As the services are being roughed-in, the guys just pull the batts out from the wall. Don't understand why the builder put them in the walls in the first place. Should have waited till all the services have been roughed-in.
Wednesday, December 8, 2010
Progress...
Progress on site has been really slow lately...partly due to the wet weather...partly due to...well, just lack of progress.
The framing to the skylights over the existing part of the house finally installed.
The deep soaker bath to the bathroom downstairs...